The following are the important points to be taken care of during cable Installation, at site

1. General : The cable should be paid off from the top of the Cable drum, held in the normal position sufficient care should be taken to prevent twists, acute bends etc, while laying the Cable.

2. Minimum Bending Radius :

  Single Core Multi Core
Cables of 1100 V Grade 15 D 12 D
Cables from 3.3 kV to 11 kV 15 D 15 D
Cable of 22 & 33 kV Grade 20 D 15 D
Where D is the overall die of the Cable.

3. Maximum Pulling Tension during Installation :

Cables having Aluminium Conductor 30 N/Sq. mm. Max
Cables having Copper Conductor 50 N/Sq. mm. Max

4. Cable Support Spacing : The disposition of cable support and its spacing should be such, as to prevent undue strain or damage to the cable.

5. Prevention of Moisture Ingress : Care should be exercised at site during installation to prevent damage to cable coverings and end which may cause the ingress of moisture.

6. Tests after Installations : Voltage withstand and Insulation Resistance Tests should be conducted on cables after laying or after jointing and terminations. The test method, voltage and duration should be as stipulated in IS: 1255-1983, for various voltage grades of the cables.

 